Mission Summary for August 25, 1999

Anthony Guillory, DC-8 Chief Scientist

Peter Hobbs, Convair 580 Chief Scientist

______________________________________________________________________

DC-8 Chief Scientist Summary
______________________________________________________________________

DC-8 Mission Scientist Report for 25 August 1999 (Julian Day 237) UTC.

The DC-8 took off at 0356 UTC on a 3 aircraft mission with the UND Citation and UW Convair 580. The aircraft were intially lined up on the back side of a line of convective cells to the SW of the Namu atoll. These cells were worked for the duration of the mission. The lines were moved to the west as the system propagated. One final leg was flown by the DC-8 along from NE to SW.

During the flight much ARMAR reported mostly light or moderate precipitation. While AMPR observed some very strong scattering in the 85 GHz channel on several passes, with brightness temperatures below 120K on one leg. AMPR also obeserved some moderate rain in the 10 GHz band on many of the legs. The CPP and CPI probes observed good and fairly large particles and concentrations on most legs.

All instruments on the DC-8 worked well on today's mission. The only failure was the FSSP probe, which failed early into the flight. However, the 2D-P probe data was intermittent. Also, the 2D-P data from a interesting segment near 0529 UTC where it detected particles ranging from 2-3 mm in size was somehow not recorded.

The DC-8 landed at 0647 UTC approx. using 2.9 flight hours leaving 61.4 hours for research use.

Mission Scientist: Anthony Guillory

______________________________________________________________________

Convair Chief Scientist Summary
______________________________________________________________________

UNIVERSITY OF WASHINGTON FLIGHT FOR KWAJEX

UNIVERSITY OF WASHINGTON FLIGHT FOR KWAJEX

DATE: 25 Aug 1999

UW FLIGHT : 1795

Goals of Flight: Coordinated flight of CV-580 with Citation and DC-8

Accomplishments : Goals achieved in several convective bands. But no data from

SPEC instruments on CV-580

Period of flight: 1550-1847

 

Approx: Local Time

(UTC=local time minus 12 hours)

Activity

LINE 1

A = 07 deg 53 min / 167 deg 14 min

B = 07 deg 18 min / 167 deg 55 min

1600

Takeoff

1602-1617

Climb to 15,000 ft heading for A

1617-1638

A -> B at 15,000 ft. Growing convection. Good example of "building block" for larger systems

LINE 2

A = 07 deg 30 min / 168 deg 42 min

B = 07 deg 45 min / 168 deg 12 min

1638-1652

To line 2 climbing to 18,000 ft

1652-1701

A -> B at 18,000 ft

1705-1713

B -> A at 15,000 ft

1717-1724

A -> near B at 12,000 ft

1729-1735

B -> A at 16,500 ft (lightning strike to radar dome).

Line 2 was a mature to decaying convective band.

LINE 3

A = 07 deg 36 min / 168 deg 23 min

B = 07 deg 48 min / 168 deg 05 min

"Backside of heavy precip" (TRMM)

1738

Heading to A climbing to 18, 000 ft

1740-1746

A -> B at 18, 000 ft

1748-1750

B -> A at 15, 000 ft

LINE 4

A = 07 deg 38 min / 168 deg 01 min

B = 07 deg 32 min / 168 min 17 min

Little activity

1751-1757

Procced to new A at 15,000 ft

1801-1808

A -> B plus at 15, 000 ft

1813-1815

B -> A at 13, 000 ft

1815-

Return to base.

1829

Good convective cell.

1830

Cumulus congestus

Instrument malfunctions:

1) SPEC CPI not aboard: being worked on by SPEC
2) SPEC HVPS not working
3) PMS 2-D prec ip probe
KWAJEX hours remaining: 51.69

Peter Hobbs